Question 1 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation A room measures 4 m × 3 m inside, with walls 0.3 m thick. The length of the centre line of the wall is
Choose your answer for question 1 A. 15.2 m B. 14.6 m C. 14.0 m D. 16.4 mAnswer and explanation Correct answer: A
The internal perimeter is 14 m. The centre line adds one wall thickness at each of the 4 corners: 14 + 4 × 0.3 = 15.2 m.
Question 2 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation Plinth area of a building is the built-up covered area measured at
Choose your answer for question 2 A. the lintel level B. the foundation level C. the floor level (plinth level) D. the roof levelAnswer and explanation Correct answer: C
Plinth area is the covered area measured at the floor level of the lowest storey, including wall thickness.
Question 3 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation To allow for voids and shrinkage, the dry volume of materials required for one cubic metre of wet concrete is taken as about
Choose your answer for question 3 A. 2.00 m³ B. 1.25 m³ C. 1.00 m³ D. 1.54 m³Answer and explanation Correct answer: D
The dry volume is about 52 to 54 percent more than the wet volume, so 1.54 is used.
Question 4 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation Approximately how many modular bricks (nominal size 20 × 10 × 10 cm) are needed for one cubic metre of brickwork?
Choose your answer for question 4 A. 600 B. 400 C. 450 D. 500Answer and explanation Correct answer: D
One brick with mortar occupies 0.2 × 0.1 × 0.1 = 0.002 m³, so 1 / 0.002 = 500 bricks.
Question 5 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation In valuation, the Years’ Purchase (YP) is the reciprocal of
Choose your answer for question 5 A. the annual rent B. the rate of interest (as a decimal) C. the rate of depreciation D. the sinking fund factorAnswer and explanation Correct answer: B
YP = 100 / i, where i is the rate of interest in percent. Capitalised value = net annual income × YP.
Question 6 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation The cross-sectional areas of an embankment at two sections 20 m apart are 20 m² and 30 m². The volume between them by the mean sectional area method is
Choose your answer for question 6 A. 1000 m³ B. 600 m³ C. 450 m³ D. 500 m³Answer and explanation Correct answer: D
Mean area = (20 + 30)/2 = 25 m². Volume = 25 × 20 = 500 m³.
Question 7 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation The cement required for one cubic metre of 1:2:4 concrete, using a dry volume factor of 1.54, is
Choose your answer for question 7 A. 0.154 m³ B. 0.44 m³ C. 0.33 m³ D. 0.22 m³Answer and explanation Correct answer: D
Sum of ratios = 7. Cement = 1.54 × 1/7 = 0.22 m³ (about 6.3 bags of 35 litres).
Question 8 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation Excavated soil swells by 25 percent. If 100 m³ of soil is excavated in its natural state, the loose volume to be carted away is
Choose your answer for question 8 A. 125 m³ B. 150 m³ C. 100 m³ D. 75 m³Answer and explanation Correct answer: A
Bulking increases the volume: 100 × 1.25 = 125 m³.
Question 9 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation A building costs ₹5,00,000 and has a scrap value of ₹50,000 after 30 years. Annual depreciation by the straight line method is
Choose your answer for question 9 A. ₹1,50,000 B. ₹14,000 C. ₹15,000 D. ₹16,667Answer and explanation Correct answer: C
Annual depreciation = (cost − scrap value)/life = (5,00,000 − 50,000)/30 = ₹15,000.
Question 10 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation Contingencies in an estimate are provided to meet
Choose your answer for question 10 A. the cost of the approved drawings B. the salary of the engineers C. unforeseen expenditure, usually about 3 to 5 percent of the estimate D. the cost of land acquisitionAnswer and explanation Correct answer: C
Contingencies cover small unforeseen items. They are generally taken as 3 to 5 percent.
Question 11 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation The volume of cement mortar needed to plaster a wall area of 20 m² with a 12 mm thick coat (ignoring wastage and the dry volume factor) is
Choose your answer for question 11 A. 2.4 m³ B. 0.24 m³ C. 0.024 m³ D. 0.12 m³Answer and explanation Correct answer: B
Volume = area × thickness = 20 × 0.012 = 0.24 m³.
Question 12 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation In the measurement of masonry, no deduction is made for openings whose area is up to
Choose your answer for question 12 A. 0.1 m² B. 1.0 m² C. 0.5 m² D. 2.0 m²Answer and explanation Correct answer: A
The rule of IS 1200 ignores small openings up to 0.1 m² (and ends of beams or joists) to keep the measurement simple.
Question 13 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation A building costing ₹6,00,000 has a scrap value of 10 percent of its cost and a life of 20 years. The annual depreciation by the straight line method is
Choose your answer for question 13 A. ₹3,000 B. ₹33,000 C. ₹30,000 D. ₹27,000Answer and explanation Correct answer: D
Scrap value = 0.1 × 600000 = ₹60000. Annual depreciation = (600000 − 60000)/20 = ₹27000.
Question 14 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation Find the quantity of earthwork excavation for a trench 20 m long, 1 m wide and 0.8 m deep.
Choose your answer for question 14 A. 16 m³ B. 36 m³ C. 20 m³ D. 24 m³Answer and explanation Correct answer: A
Volume = 20 × 1 × 0.8 = 16 m³.
Question 15 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation A building has a plinth area of 10 m × 6 m. At a plinth area rate of ₹20000 per m², the approximate cost is
Choose your answer for question 15 A. ₹12,00,000 B. ₹6,40,000 C. ₹24,00,000 D. ₹1,20,000Answer and explanation Correct answer: A
Cost = plinth area × rate = 60 × 20000 = ₹12,00,000.
Question 16 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation Find the quantity of earthwork excavation for a trench 25 m long, 1.2 m wide and 1.5 m deep.
Choose your answer for question 16 A. 45 m³ B. 9 m³ C. 450 m³ D. 135 m³Answer and explanation Correct answer: A
Volume = 25 × 1.2 × 1.5 = 45 m³.
Question 17 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation A room has internal dimensions 6 m × 3 m and walls 0.2 m thick. The length of the centre line of the walls is
Choose your answer for question 17 A. 18.8 m B. 18.4 m C. 19.6 m D. 18 mAnswer and explanation Correct answer: A
Centre line length = internal perimeter + 4 × thickness = 18 + 4 × 0.2 = 18.8 m.
Question 18 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation The estimated cost of a work is ₹1,00,000. After adding 10 percent for contingencies, the total estimate is
Choose your answer for question 18 A. ₹2,00,000 B. ₹10,000 C. ₹90,000 D. ₹1,10,000Answer and explanation Correct answer: D
Total = 100000 × (1 + 10/100) = ₹1,10,000.
Question 19 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation One cubic metre of 1:2:4 concrete needs 6.4 bags of cement (₹450 per bag), 0.44 m³ of sand (₹1500 per m³), 0.88 m³ of aggregate (₹1600 per m³) and labour of ₹1200. The cost per cubic metre is
Choose your answer for question 19 A. ₹4948 B. ₹6763 C. ₹7180 D. ₹6148Answer and explanation Correct answer: D
Cement = 6.4 × 450 = 2880; sand = 0.44 × 1500 = 660; aggregate = 0.88 × 1600 = 1408; labour = 1200. Total = ₹6148.
Question 20 · Civil Engineering (SSC JE) · Estimating, Costing and Valuation A square footing is tapered like a frustum of a pyramid with a base 3 m × 3 m, a top 0.6 m × 0.6 m and a height of 0.4 m. Its volume is
Choose your answer for question 20 A. 1.872 m³ B. 3.6 m³ C. 1.488 m³ D. 1.248 m³Answer and explanation Correct answer: C
V = h/3 (A1 + A2 + √(A1 A2)) = 0.4/3 × (9 + 0.36 + 1.8) = 1.488 m³.